Summary
Description - Updates to all Annexes and the Implementation Plan will occur on a rolling basis throughout the project, following internal monitoring and reporting periods (every 6 months). A final Updated Project Implementation Plan and Annexes, presented as a PDF, will be compiled to include all modifications as well as changes log that provides an overview of changes and/or additions made over the course of the project.
A key Annex – the Risk Management Plan - is to be added to the Implementation Plan in M7. This document will address possible risks for the completion of WP/Actions/Tasks/Deliverables and establish a plan of response. Addressed in the plan:
the identification of risks,
their location (internal to the BAMB project or external),
their probability,
their impact, and
measures taken to address/minimize the risks