Final demo-unit commissioned at WAT-site

Summary
The pilot installation will be placed next to WAT’s biogas plant in Amsterdam. The operators for the site, WAT will oversee the location preparation for the delivery and installation of the plant assembled at FRA’s workshop. The outcome of Task 2.2.2 will give the necessary information for the site preparation. In particular, they will perform the required civil works and prepare the utility connections with the hosting plant (e.g. instrument air, electricity connection, CO2 supply by connecting a gas line from the biogas separation plant (WAT) to the pilot facility, wastewater drainage, etc.). Furthermore, WAT will arrange the permitting necessary for the installation.